Concrete Calculator

In this guide
  1. How this calculator works
  2. How to measure for concrete
  3. How much concrete for common slabs
  4. Bags or a ready-mix truck?
  5. Worked example: 20 x 10 ft patio
  6. What changes the cost
  7. Related cost guides
  8. Where the prices come from
  9. Common questions

Enter the size of your slab, patio or post holes to see how many cubic yards or bags of concrete you need and what ready-mix costs. A 20 by 10 ft patio at 4 inches thick takes about 2.5 cubic yards, or 2.7 with 10% extra.

1. What are you pouring?
Shape

Patios 4 in, driveways 4 to 6 in.

2. Costs to include

If quotes near you tend to run high or low, adjust every price at once.

Edit the prices (use your own quote)

These are national installed prices. Type in the numbers from your quote and the estimate updates.

ItemLow $High $
Ready-mix concrete (per cubic yard) (per cu yd)
Short-load fee (per cubic yard under the truck minimum)
Pro pour and finish (per sq ft of slab)

Estimated cost

– to –

How this calculator works

For a slab, volume is length times width times thickness (inches divided by 12), in cubic feet. Divide by 27 to get cubic yards. For round holes, it uses pi times the radius squared times the depth. An 80 lb bag makes about 0.60 cu ft, a 60 lb bag about 0.45 and a 40 lb bag about 0.30.

How to measure for concrete

Concrete is ordered by volume, so you need three measurements. Measure inside the forms if they’re already built:

  1. Slabs, patios and driveways: length and width in feet, thickness in inches. Split an L-shape into two rectangles and run each one.
  2. Round footings and post holes: hole diameter in inches, depth in feet, and the number of holes.
  3. Extra: the calculator adds 10% for spills, uneven ground and form flex. Raise it if the subgrade is rough.

The math: cubic feet = length x width x (thickness ÷ 12). Divide by 27 for cubic yards. HomeGuide notes that one cubic yard covers about 81 sq ft at 4 inches thick, which is a handy check.

How much concrete for common slabs

All at 4 inches thick, the usual depth for patios, walkways and garage floors:

Slab sizeCubic yardsWith 10% extra80 lb bags (with extra)Ready-mix at $110 to $165/yd
10 x 10 ft1.231.3662$149 to $224
12 x 12 ft1.781.9689$215 to $323
20 x 10 ft2.472.72123$299 to $448
20 x 20 ft4.945.43245$598 to $896
24 x 24 ft7.117.82353$860 to $1,290
Calculator math. Ready-mix price is the calculator’s starting range and excludes short-load fees and labor.

Going thicker adds up fast: 6 inches needs 50% more concrete than 4 inches. For driveway thickness, reinforcement and installed prices, see our concrete driveway cost guide.

Bags or a ready-mix truck?

Bags look cheap per bag but add up by the yard. LawnLove and HomeGuide list an 80 lb bag of high-early-strength mix at $6.29. A truck charges $110 to $165 per yard, but suppliers often add a short-load fee of $40 to $60 for every yard under a 10-yard load. Here is how that plays out:

Concrete needed80 lb bagsBag costTruck cost (with short-load fee)
0.5 cu yd23 (1,840 lb)$145$435 to $653
1 cu yd45 (3,600 lb)$283$470 to $705
2 cu yd90 (7,200 lb)$566$540 to $810
3 cu yd135 (10,800 lb)$849$610 to $915
5 cu yd225 (18,000 lb)$1,420$750 to $1,130
Bag count: cubic feet ÷ 0.6 per 80 lb bag. Bag price $6.29 (LawnLove, Dec 2025; HomeGuide, Jan 2026). Truck: calculator starting prices for ready-mix and short-load fees with a 10-yard minimum. Some suppliers charge a flat short-load fee of $60 to $110 instead (LawnLove).

Up to about 1 to 2 cubic yards, bags usually cost less in cash, but 90 bags means mixing and lifting 7,200 lb by hand. Past 2 to 3 yards, a truck wins on both price and labor. Small pours can also be split with a neighbor or a second project to fill the truck.

Worked example: 20 x 10 ft patio

Worked example: 20 x 10 ft patio, 4 inches thick. Volume: 20 x 10 x (4 ÷ 12) = 66.7 cu ft. With 10% extra: 73.3 cu ft ÷ 27 = 2.72 cu yd. Ready-mix: 2.72 x $110 to $165 = $299 to $448. Short-load fee: 7.28 yd under the 10-yard minimum x $40 to $60 = $291 to $437. Pro pour and finish: 200 sq ft x $8 to $18 = $1,600 to $3,600. Total with a crew: $2,190 to $4,490. In bags, the same pour takes 123 bags of 80 lb, about 10,630 lb of concrete.

20 x 10 ft patio at 4 inches: where the money goes

Ready-mix only: $299 to $448

Ready-mix + short-load fee: $590 to $885

Pro pour and finish only: $1,600 to $3,600

All of it: $2,190 to $4,490

Scale: $0 to $5,000. Calculator starting prices: ready-mix $110 to $165 per yard, short-load $40 to $60 per missing yard, pour and finish $8 to $18 per sq ft.

Setting posts instead? Eight 10 inch holes, 3 ft deep, take 13.1 cu ft, or 14.4 cu ft with 10% extra. That is 24 bags of 80 lb, a job where bags clearly beat a truck.

What changes the cost

  • Ready-mix price. About $110 to $165 per cubic yard before delivery fees.
  • Short loads. Orders smaller than a full truck (about 9 to 10 yards) often carry a fee of roughly $40 to $60 per missing yard.
  • Labor. Hiring a crew to pour and finish a slab adds about $8 to $18 per sq ft.
  • Extras. Weekend delivery, long unloading waits and fuel surcharges add more.

Where the prices come from

The starting prices are U.S. national installed ranges from 2025 and 2026 cost guides. Open Edit the prices in the calculator to replace any of them with the numbers from your own quote.

Other sources used on this page:

Common questions

How many bags of concrete make a cubic yard?

About 45 bags of 80 lb, 60 bags of 60 lb, or 90 bags of 40 lb.

When should I order a truck instead of bags?

Past about one cubic yard, ready-mix is usually cheaper and far less work than mixing dozens of bags by hand.

How thick should a concrete slab be?

4 inches is standard for patios, walkways and garage floors. Driveways are often 4 to 6 inches.

How much concrete do I need for a 10 x 10 slab?

At 4 inches thick, a 10 x 10 slab takes 33.3 cu ft, or 1.23 cubic yards. With 10% extra that is 1.36 cubic yards, or about 62 bags of 80 lb.

How much does a cubic yard of concrete weigh?

About 3,900 to 4,100 lb, or roughly 2 tons. The calculator uses 145 lb per cubic foot (3,915 lb per yard), and HomeGuide puts a yard at about 2.03 tons.